top of page

Junction 42
Wastewater Force Main

Red Deer County

Project Description

The scope of work for this project includes the installation of new sanitary force main system. Through detailed review of sanitary servicing options, it was determined that teaming up with the Town of Penhold, a neighbouring municipality, would provide significant advantages to both parties in providing needed servicing to areas which could not be serviced by current infrastructure. Cooperation between the municipalities provided the shortest connection length to the SRDRWC system. Tagish completed the design and construction administration of over 1.1 km force main and over 1.5km of sanitary gravity main. This project was an important improvement that will help to ensure the proper conveyance and treatment of wastewater in the area.

Location

Red Deer County

Sectors

ALL_TAG.png

Highlights

  • 1,070m of 150mm dia. sanitary force main

  • 1,070m of 300mm dia. sanitary force main

  • 1,930m of sanitary gravity main (200mm dia - 450mm dia)

  • 60 vert.m of sanitary manholes


bottom of page